Moore Square Renovation Moves Forward; Apparent Low Bid Awaits Council Approval

Moore Square Renovation Moves Forward; Apparent Low Bid Awaits Council Approval

Work on the Moore Square renovation could get underway in late October now that Raleigh parks staff have chosen a Sanford company, American South General Contractors, as the apparent low bidder at $14.279 million.

With a contract guarantee of thirteen months from the date the city sends its “notice to proceed” to the company, the often-moved completion date becomes November 2018, parks planners said.

The Raleigh City Council has final say over the bid and will likely consider awarding the contract at an August meeting, parks staff say.

“At the latest we will bring the bid award to the City Council on Sept. 5,” park planner Grayson Maughan says in an email Thursday.…

Click to read...  Wilson drying out and cleaning up after flooding this week